Question No: 71 – (Topic 1)

Which of the following frameworks describes a standard for processes within business information management at the strategy, management and operations level?

  1. Val IT

  2. BISL

  3. COBIT

  4. TOGAF

Answer: B

Question No: 72 – (Topic 1)

You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your project. Which risk management process can satisfy management#39;s objective for your project?

  1. Quantitative analysis

  2. Qualitative risk analysis

  3. Historical information

  4. Rolling wave planning

Answer: B

Question No: 73 – (Topic 1)

Which of the following are the roles of a CEO in the Resource management framework? Each correct answer represents a complete solution. Choose all that apply.

  1. Organizing and facilitating IT strategic implementations

  2. Establishment of business priorities amp; allocation of resources for IT performance

  3. Overseeing the aggregate IT funding

  4. Capitalization on knowledge amp; information

Answer: A,B,D

Question No: 74 – (Topic 1)

Which of the following are parts of SWOT Analysis? Each correct answer represents a complete solution. Choose all that apply.

  1. Optimism

  2. Threats

  3. Weaknesses

  4. Opportunities

  5. Tools

  6. Strengths

Answer: B,C,D,F

Question No: 75 – (Topic 1)

Which of the following types of IT organizational structures states that all IT decision making and the IT budget are in one place, much easier to manage, and require much less effort to organize?

  1. Decentralized

  2. Federated

  3. Project-based

  4. Centralized

Answer: D

Question No: 76 – (Topic 1)

Elizabeth is a project manager for her organization and she finds risk management to be very difficult for her to manage. She asks you, a lead project manager, at what stage in the project will risk management become easier. What answer best resolves the difficulty of risk management practices and the effort required?

  1. Risk management only becomes easier the more often it is practiced.

  2. Risk management only becomes easier when the project is closed.

  3. Risk management is an iterative process and never becomes easier.

  4. Risk management only becomes easier when the project moves into project execution.

Answer: A

Question No: 77 – (Topic 1)

Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process.

During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?

  1. The events should be determined if they need to be accepted or responded to.

  2. The events should be entered into the risk register.

  3. The events should continue on with quantitative risk analysis.

  4. The events should be entered into qualitative risk analysis.

Answer: B

Question No: 78 – (Topic 1)

Which of the following is NOT a valid maturity level of the Software Capability Maturity Model (CMM)?

  1. Repeatable level

  2. Managed level

  3. Defined level

  4. Fundamental level

Answer: D

Question No: 79 – (Topic 1)

You are hosting a collection of stakeholders from across the organization to identify the ideas and attitudes about your company#39;s help desk. You want the stakeholders to honestly share their opinions about the help desk service so you can identify problems, solutions, and take actions to improve the service. What type of requirements elicitation activity is this?

  1. Root cause analysis

  2. Stakeholder analysis

  3. Focus groups

  4. Workshop

Answer: C

Question No: 80 – (Topic 1)

Which of the following concepts is a semi-standard structured report supported by proven design methods and automation tools that can be used by managers to keep track of the

execution of activities by staff within their control and monitor the consequences arising from these actions?

  1. Total Security Management

  2. Balanced Scorecard (BSC)

  3. Total Quality Management

  4. Six Sigma

Answer: B

100% Free Download!
Download Free Demo:CGEIT Demo PDF
100% Pass Guaranteed!
Download 2018 Latesttests CGEIT Full Exam PDF and VCE

Latesttests ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2018 Latesttests IT Certification PDF and VCE