[Free] 2017(Sep) CollectDumps Dumpsleader GIAC GCPM Dumps with VCE and PDF 31-40

CollectDumps 2017 Sep GIAC Official New Released GCPM
100% Free Download! 100% Pass Guaranteed!
http://www.CollectDumps.com/GCPM.html

Topic 1, Volume A

Question No: 31 – (Topic 1)

You are the project manager of a project to create a network inside of a building. You need to hire an electrician to run network cable throughout the building. Based on your experience, you create an estimate for the work that you#39;ll measure all of the bids against. This is an example of what type of procurement seller selection?

  1. Seller rating system

  2. Independent estimate

  3. Weighting system

  4. Screening system

Answer: B

Question No: 32 – (Topic 1)

Sam is the project manager for his organization. His project is not doing well on project schedule performance, and management wants him to predict how the project schedule and cost will end. Management has asked Sam to report and forecast his project#39;s performance based on the Delphi Method, scenario building, technology forecasting, and to forecast by analogy. What forecasting method is management asking Sam to use?

  1. Earned value management method

  2. Time series methods

  3. Causal/econometric methods

  4. Judgmental methods

Answer: D

Question No: 33 – (Topic 1)

You are the project manager for your organization and would like to use a time and materials contract for a small project. What must a time and materials contract have to safeguard the project?

  1. Terms for payment

  2. Approval from the project sponsor

  3. An approved vendor by a leading trade organization

  4. A not-to-exceed clause

Answer: D

Question No: 34 – (Topic 1)

You work as a project manager for PassGuide Inc. You want to improve the competencies and interaction of team members to enhance project performance. Which of the following processes will help you to accomplish the task?

  1. Manage Project Team

  2. Acquire Project Team

  3. Develop Project Team

  4. Develop Human Resource Plan

Answer: C

Question No: 35 CORRECT TEXT – (Topic 1)

Fill in the blank with the appropriate term.

The defines the period in which, during the development of the project scope statement, a clear and very thorough project scope statement narrative is documented.

Answer: develop project scope statement period

Question No: 36 – (Topic 1)

You are the project manager of the JKM Project for your organization. Your project is

supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you#39;ll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project#39;s current cost performance index (CPI) is. What value should you report to management based on your project#39;s performance?

A. $306,000

B. .75

C. .94

D. $344,250

Answer: C

Question No: 37 – (Topic 1)

You work as a project manager for PassGuide Inc. You want to include a budget contingency to accommodate the risk of incurring unidentifiable but normally occurring costs within the defined scope. Which of the following processes will help you to accomplish the task?

  1. Cost controlling

  2. Cost budgeting

  3. Cost baselining

  4. Cost estimation

Answer: C

Question No: 38 – (Topic 1)

Which of the following are the types of casual/econometric forecasting methods? Each correct answer represents a complete solution. Choose all that apply.

  1. ARIMA

  2. Econometrics

  3. ARMA

  4. Scenario building

Answer: A,B,C

Question No: 39 – (Topic 1)

Which of the following documents is described in the statement below?

quot;It is an exchange of promises between two or more parties to do an act which is enforceable in the court of law.quot;

  1. Risk register

  2. Contract

  3. Project calendar

  4. Resource calendar

Answer: B

Question No: 40 CORRECT TEXT – (Topic 1)

You work as a project manager for PassGuide Inc. You are using market risk, value at risk (VaR), historical simulation (HS), and extreme value theory (EVT) so as to analyze a portfolio and make forecasts of the likely losses that would be incurred for a variety of risks. Which of the following processes are you using to accomplish the task?

Answer: Risk limitation Answer: Risk modeling Answer: Risk exposure Answer: Risk threshold Answer: B

100% Free Download!
Download Free Demo:GCPM Demo PDF
100% Pass Guaranteed!
Download 2017 CollectDumps GCPM Full Exam PDF and VCE

CollectDumps ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 CollectDumps IT Certification PDF and VCE