[Free] 2017(Sep) CollectDumps Dumpsleader GIAC GCPM Dumps with VCE and PDF 211-220

CollectDumps 2017 Sep GIAC Official New Released GCPM
100% Free Download! 100% Pass Guaranteed!
http://www.CollectDumps.com/GCPM.html

Topic 1, Volume A

Question No: 211 – (Topic 3)

You are the project manager for PassGuide Inc. Your project has a budget at completion of

$950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone.

What is the project#39;s cost performance index?

A. 0.84

B. 0.86

C. 0.98

D. 0.95

Answer: D

Question No: 212 – (Topic 3)

Which of the following individuals strategically handles the human resource tools and assists the organization in attracting talented people for the required job?

  1. HR manager

  2. Stakeholder

  3. Project manager

  4. Change manager

Answer: A

Question No: 213 – (Topic 3)

Which of the following is described in the statement below?

quot;It is a form of discussion held in person or by electronic means. Its goal is to come to a written agreement regarding a business matter.quot;

  1. Agreement

  2. Project charter

  3. Contract negotiation

  4. Scope

Answer: C

Question No: 214 – (Topic 3)

Micha is the project manager for her project. Micha is now ready to complete the scope verification process so that she can move the project into the project closing process. What is the primary purpose of the scope verification process?

  1. Review of the project performance

  2. Acceptance of the project deliverables

  3. Acceptance of the project team#39;s performance

  4. Approval that the project has met its objectives

Answer: B

Question No: 215 – (Topic 3)

Which of the following theories states that humans have five needs and the needs above

the hierarchy cannot be met until the lower needs are met?

  1. Maslow#39;s Hierarchy of Needs

  2. Ouchi#39;s Theory Z

  3. McGregor#39;s Theory of X and Y

  4. Expectancy Theory

Answer: A

Question No: 216 – (Topic 3)

You work as a project manager for BlueWell Inc. Management has asked you to work with the key project stakeholder to analyze the risk events you have identified in the project.

They would like you to analyze the project risks with a goal of improving the project#39;s performance as a whole.

What approach can you use to achieve the goal of improving the project#39;s performance through risk analysis with your project stakeholders?

  1. Focus on the high-priority risks through qualitative risk analysis

  2. Use qualitative risk analysis to quickly assess the probability and impact of risk events

  3. Involve the stakeholders for risk identification only in the phases where the project directly affects them

  4. Involve subject matter experts in the risk analysis activities

Answer: A

Question No: 217 – (Topic 3)

You work as a project manager for PassGuide Inc. Your project is in a situation in which a party interested in trading an asset is unable to do so. Which of the following types of risks must have occurred in the above scenario?

  1. Market risk

  2. Financial risk

  3. Pure risk

  4. Liquidity risk

Answer: D

Question No: 218 – (Topic 3)

Which of the following processes is described in the statement below?

quot;It is the process of identifying and documenting relationships among the project activities.quot;

  1. Sequence Activities

  2. Define Scope

  3. Create WBS

  4. Define Activities

Answer: A

Question No: 219 – (Topic 3)

Which of the following statements on conflicts is NOT true?

  1. They are natural and force a search for alternatives.

  2. Conflicts are an individual#39;s issue.

  3. Conflict resolution should focus on the present, not the past.

  4. Openness resolves conflicts.

Answer: B

Question No: 220 – (Topic 3)

You work as a project manager for PassGuide Inc. You are involved in the cost management work for the project. George, one of the newly joined team members, wants to know the processes involved in the project cost management work. What will you tell George?

Each correct answer represents a complete solution. Choose all that apply.

  1. Estimate costs

  2. Control costs

  3. Perform quality assurance

  4. Determine budget

Answer: A,B,D

100% Free Download!
Download Free Demo:GCPM Demo PDF
100% Pass Guaranteed!
Download 2017 CollectDumps GCPM Full Exam PDF and VCE

CollectDumps ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 CollectDumps IT Certification PDF and VCE