Topic 1, Volume A

Question No: 201 – (Topic 3)

You work as a project manager for PassGuide Inc. You want to improve the competencies

and interaction of team members to enhance project performance. Which of the following processes will help you to accomplish the task?

  1. Acquire Project Team

  2. Develop Project Team

  3. Manage Project Team

  4. Develop Human Resource Plan

Answer: B

Question No: 202 – (Topic 3)

Which of the following tasks are NOT part of the project execution phase? Each correct answer represents a complete solution. Choose two.

  1. Making an expected resources list

  2. Reviewing issues tracking logs

  3. Creating a baseline schedule

  4. Reviewing a schedule baseline

Answer: A,C

Question No: 203 – (Topic 3)

Hank is a project manager for the NHY Project. His project has a very tight budget with little room for project overruns on costs. Hank needs to control costs and reduce expenses as much as possible within the project in order for the project to be deemed successful in the organization. On the NHY Project, Hank is using many contractors that are integrated into the project team. What can Hank do to keep project costs down in this scenario?

  1. Release the project contracted employees as soon as they have fulfilled their project obliga tions.

  2. Trim the project scope.

  3. Increase the quality control testing activities.

  4. Release the project contractors and hire full-time employees.

Answer: A

Question No: 204 – (Topic 3)

You work as a project manager for PassGuide Inc. You are using the three point estimate to calculate the estimated activity durations for your project. If you have an optimistic estimate of 10 days, a pessimistic estimate of 19 days, and a most likely estimate of 13, which of the following is the expected activity duration for your project?

A. 16.5

  1. 18

  2. 17

D. 17.5

Answer: A

Question No: 205 – (Topic 3)

Which of the following is a document that covers the work that will be done, how the work will be compensated, and any penalties for noncompliance?

  1. Contract

  2. Project description

  3. Cost baseline

  4. Control chart

Answer: A

Question No: 206 – (Topic 3)

Which of the following processes describes the statement below?

quot;It consists of the processes required to ensure that the project contains all the work required to complete the project effectively.quot;

  1. Project communications management

  2. Risk management

  3. Project scope management

  4. Project human resource management

Answer: C

Question No: 207 – (Topic 3)

Tom works as the project manager for BlueWell Inc. He spends the majority of his time communicating with team members and the project stakeholders. Various communication skills are involved in the communication processes. Which communication skills are involved in this process?

Each correct answer represents a part of the solution. Choose all that apply.

  1. Formal and Informal

  2. Vertical and Horizontal

  3. Internal and External

  4. Confronting and problem solving

Answer: A,B,C

Question No: 208 – (Topic 3)

Which of the following are outputs of the Develop Project Team process? Each correct answer represents a complete solution. Choose all that apply.

  1. Team performance assessment

  2. Project management plan

  3. Enterprise environmental factors update

  4. Project staff assignment

Answer: A,C

Question No: 209 – (Topic 3)

Which of the following is described in the statement below?

quot;It means that feedback regarding performance is provided to the person being evaluated from many sources, including superiors, peers, and subordinates.quot;

  1. 360-degree evaluations

  2. Goal review

  3. Team-led project reviews

  4. Organizational performance appraisals

Answer: A

Question No: 210 – (Topic 3)

Which of the following best describes the identification, analysis, and ranking of risks?

  1. Fixed-price contracts

  2. Plan Risk management

  3. Fast tracking

  4. Design of experiments

Answer: B

100% Free Download!
Download Free Demo:GCPM Demo PDF
100% Pass Guaranteed!
Download 2017 CollectDumps GCPM Full Exam PDF and VCE

CollectDumps ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 CollectDumps IT Certification PDF and VCE