Topic 1, Volume A

Question No: 131 – (Topic 2)

Which of the following are outputs of the Perform Integrated Change control process? Each correct answer represents a complete solution. Choose all that apply.

  1. Work performance information

  2. Project management plan update

  3. Project document update

  4. Change request status update

Answer: B,C,D

Question No: 132 – (Topic 2)

You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

  1. Decomposition

  2. Rolling wave plan

  3. Templates

  4. Precedence diagramming method

Answer: D

Question No: 133 – (Topic 2)

You work as a project manager for PassGuide Inc. Your project has a budget of $545,000 and is expected to last 12 months. You have identified several risk events and created risk response plans for your project. In which of the following process groups will you be able to implement risk response plans?

  1. Planning

  2. Initiating

  3. Executing

  4. Monitoring and controlling

Answer: D

Question No: 134 – (Topic 2)

You work as a project manager for PassGuide Inc. You are working on a construction project. You are compiling and reviewing the comments to draft deliverables prior to forwarding them to the contractor for incorporation into the final draft. You are responsible for communicating the changes to the reviewer who initially made the comments. Who among the following will be responsible for updating the draft deliverables and producing the final deliverables in the above scenario?

  1. Contractor

  2. Project manager

  3. Reviewer

  4. Risk manager

Answer: A

Question No: 135 – (Topic 2)

You work as a project manager for PassGuide Inc. You are concerned with defining and controlling what is or is not included in the project. Which of the following processes will you use to accomplish the above task?

  1. Project scope management

  2. Risk management

  3. Project communications management

  4. Project reporting structure

Answer: A

Question No: 136 – (Topic 2)

Which of the following techniques is described in the statement below?

quot;It is used to verify whether a particular work can best be accomplished by the project team or must be purchased from outside sources.quot;

  1. Contract type

  2. Expert judgment

  3. Make-or-Buy analysis

  4. Risk analysis

Answer: C

Question No: 137 – (Topic 2)

Which of the following is described in the statement below?

quot;It is a group of sequential and related project phases that are defined by the organization and control needs of the management or organizations concerned with the project, the nature of the project itself, and the application area.quot;

  1. Project life cycle

  2. Verify scope

  3. Activity list

  4. Project charter

Answer: A

Question No: 138 – (Topic 2)

Mark works as a project manager for PassGuide Inc. The change control board has approved several scope changes that will drastically alter his project plan. There are also some changes caused to the project risks, communication, and vendors. Which of the following should also be updated based on the above scope changes?

  1. Process improvement plan

  2. Quality baseline

  3. Vendor selection process

  4. Stakeholders identification

Answer: B

Question No: 139 – (Topic 2)

Wanda is the project manager for her organization and is creating a checklist for her project team.

In this project the team will be installing electrical fixtures throughout an office building and she wants to confirm that the installations will be done correctly each time. Her goal is that the project deliverables will be of quality throughout the project installation process. In what project process will Wanda#39;s team use the checklist?

  1. Planning quality

  2. Project execution

  3. Quality assurance

  4. Quality control

Answer: D

Question No: 140 – (Topic 2)

You are the project manager for your organization and would like to use a time and materials contract for a small project. What must a time and materials contract have to safeguard the project?

  1. Terms for payment

  2. A not-to-exceed clause

  3. An approved vendor by a leading trade organization

  4. Approval from the project sponsor

Answer: B

100% Free Download!
Download Free Demo:GCPM Demo PDF
100% Pass Guaranteed!
Download 2017 CollectDumps GCPM Full Exam PDF and VCE

CollectDumps ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 CollectDumps IT Certification PDF and VCE